CASE STUDY | VMware → OpenNebula + StorPool
From Daily Outages to Zero Platform Downtime
How Nubius Solutions migrated 180 production-critical virtual machines from VMware and continues to help the customer move workloads to OpenNebula and StorPool.
180
VMs migrated to date across Dev, QA and Production
0
platform-caused outages during the first six months of operation
~10 min
customer QA per VM, down from hours or days
3–5 min
downtime per stateless VM at cutover
2 weeks
from hardware purchase to a platform ready for VMs
5 days
to source and deliver hardware amid market shortages
Customer: An industry-leading SaaS provider whose applications help utility companies communicate with their retail and commercial customers, often during storms and service emergencies.
Starting point: VMware on 11 hosts (64 cores and 500 GB RAM each), backed by roughly 150 TB of QNAP storage, in the customer’s own data center space.
Solution: OpenNebula virtualization with StorPool fully managed storage.
Nubius role: Risk assessment, architecture, hardware sourcing support, migration tooling and execution, and ongoing managed services for the data center.
Twelve hours
The platform was down, with no confident plan for recovery. Every virtual machine depending on the storage array was out of service, across all environments: Development, QA and, most critically, Production. For a company whose applications help utilities communicate with their customers, often during storms and service emergencies, this “IT problem” immediately became a major business problem. The impact of the outage landed directly on the customer’s customers.
Eight hours into the outage, Nubius Solutions was called in to help recover the environment. The full outage lasted about 12 hours. Resolution of the outage exposed how fragile the platform had become.
The Challenge
The environment had not been neglected. It had outgrown its architecture, and every month it continued operating it carried more risk:
- Storage that was never built for this. The QNAP array failed repeatedly, and every failure took down multiple production virtual machines at once. Outages of 40 minutes to 2 hours were occurring on nearly a daily basis.
- Reputation on the line. Each outage reached end users and wore down the trust of the utility companies the business served.
- A licensing dead end. VMware ran on a perpetual license with no vendor support and no high availability. After Broadcom’s licensing changes, renewing meant a 3-year subscription commitment and deeper vendor lock-in. All it would have added was the option to enable HA. It would not have fixed the storage issues, or any of the other underlying issues.
- Aging hardware at the worst possible time. Replacing everything at today’s hardware prices was not an option, especially for infrastructure the company planned to leave eventually.
The long-term plan for the environment was clear: move to cloud-native applications. But the unstable platform was pushing teams to rush that move, and rushed migrations bring errors and poor deployments. Once the dust settled after the outage, the company realized they needed a bridge: an interim environment that was stable, cost-effective, deliverable within months, and without a large capital commitment.
The Solution: OpenNebula + StorPool, delivered by Nubius
Nubius proposed replacing the platform, not patching it. OpenNebula replaces VMware as the virtualization layer for migrated workloads. StorPool, delivered as a fully managed storage service, replaced the QNAP array, which was the root cause of most incidents. As an official partner of both OpenNebula and StorPool, Nubius designed the solution, brought it together and continues to support the migration.
The design reused everything it could. The only new hardware was 3 servers dedicated to StorPool. As each VMware host was emptied, Nubius converted it into an OpenNebula node, so the existing hosts kept working on the new platform. The ongoing managed service by Nubius, including StorPool storage and monitoring, was provided on month to month terms, providing flexibility for future options.
How Nubius Delivered
Nubius does not show up and start migrating. Every engagement follows a six-phase framework designed to remove uncertainty and protect the business at each step. Here is how each phase played out, and the obstacles it overcame.
Phase 1 — Discovery & Assessment
After the outage, Nubius went on site at the data center to assess the full environment: hosts, storage, networking, workloads and dependencies. Every risk area was documented, and the findings became the foundation of the proposed solution. Result: decisions based on evidence, not assumptions.
Phase 2 — Architecture & Readiness
With the architecture approved, the next obstacle was the market itself. Server components and enterprise disks were in global short supply, and vendor lead times put the whole timeline at risk. Nubius worked alongside the customer’s team to source cost-effective servers and the right disks for the storage tier, with proposals delivered within 24 hours and all hardware on site within 5 business days of the order.
Nubius then worked with the customer’s NetOps team on the physical installation. The OpenNebula build was done by a senior Engineer Nubius has worked with on multiple projects, following Nubius’s design and direction. The StorPool cluster was configured jointly with StorPool. Within 2 weeks of the hardware purchase, the platform was ready for its first VMs.
Phase 3 — Kickoff & Alignment
A process change can stall a project as easily as a technical issue. The customer’s teams first planned hours, and in some cases days, of application QA per server. Nubius proposed a different approach: start with Development servers and let the teams see the process for themselves. Because Nubius converts the disk instead of rebuilding the server, nothing inside it changes: same OS, same libraries, same packages, same IP address.
After a few Development rounds and a review with executives, the teams trusted the process. Customer-side validation dropped to about 10 minutes per server, as a second check after Nubius’s own full validation. Maintenance windows were limited to Tuesdays and Thursdays, and the plan was built around that.
Phase 4 — Implementation
Nubius built a fully automated conversion process tailored to the customer’s environment. It copies the VM, converts it to KVM, uploads the image to OpenNebula, removes VMware components, installs OpenNebula components and reconfigures networking so the server keeps its exact IP address. Variations handle different operating systems, from legacy CentOS 7 to current Rocky Linux and AlmaLinux, Debian and Ubuntu.
- Preparation runs while the server is still in service. The initial disk sync can take hours, depending on disk size and bandwidth, but the source server stays online the whole time.
- Stateless servers: the full conversion runs ahead of time. The cutover takes about 10 minutes, with only 3–5 minutes of downtime: power off the old server, start the new one.
- Stateful servers: an incremental final sync captures the last changes, bringing the cutover to 25–40 minutes depending on data size.
- A repeatable runbook: pre-migration validation records the server’s state and running services, then the cutover, then a post-migration validation that compares the results to confirm the server runs exactly as before.
With this process, stateless servers moved at a steady 5–6 per one-hour maintenance window, while extended windows of up to 8 hours handled 8–10 stateful servers in a single day. The 180 virtual machines described here moved in 23 waves, averaging about 8 servers each: 3 Development, 5 QA and 15 Production, with some waves scheduled on weekends to keep pace. Production waves were coordinated with the customer and their end users.
Phase 5 — Validation & Stabilization
Real environments have edge cases, and the process was built to absorb them without putting Production at risk. Across the 180 virtual machines described here, there was one rollback, caused by the customer’s configuration management, not the migration. A Puppet rule auto-updated packages at boot and changed the converted server. Nubius rolled it back within the window, the setting was fixed on the source VM, and a Puppet check was added to pre-migration validation for every server after that.
Other edge cases, such as misconfigurations and leftovers from end-of-life systems, were caught before cutover. Those servers moved to the next wave, the tooling was adjusted, and they were migrated successfully. No rollback was caused by the migration process itself.
Phase 6 — Handoff & Ongoing Operations
Nubius continues to help the customer migrate workloads from VMware to OpenNebula and StorPool. Nubius manages the customer’s on-premises data center under a managed services agreement: monitoring the platform and its servers, responding at the infrastructure and network layers, and coordinating StorPool and specialist engineers when needed. Organizations that want vendor-backed OpenNebula support can also get OpenNebula subscriptions from Nubius as part of a fully managed service.
The Results
| Before | After | |
|---|---|---|
| Platform outages | At their worst, daily outages of 40 minutes to 2 hours, plus a 12-hour full outage | Zero platform-caused outages during the first six months of operation |
| Hypervisor | VMware perpetual license, no vendor support, no HA | OpenNebula for migrated workloads; migration from VMware continues |
| Storage | QNAP, the root cause of repeated failures | StorPool, delivered as a fully managed service |
| Commitment | Renewal meant a 3-year subscription and vendor lock-in, adding only the option for HA | Month-to-month managed service; existing hosts reused as OpenNebula nodes |
| Downtime per server | — | 3–5 min (stateless); 25–40 min cutover (stateful) |
| Customer QA per server | Originally planned at hours to days | About 10 minutes, as a second check after Nubius validation |
Note: 180 virtual machines have been migrated across Development, QA and Production. Obsolete servers were decommissioned as part of the work. Nubius continues to assist the customer with migration of the remaining workloads from VMware to the new platform.
The new platform recorded zero platform-caused outages during its first six months of operation, with no virtual machine failures or storage incidents caused by the platform during that period.
The Bigger Picture
The real win is not the new platform. It is what the platform makes possible. Development teams can now move to cloud-native applications deliberately and on their own schedule, without an unstable environment forcing rushed and error-prone moves.
This story is not unique. Many organizations running aging VMware infrastructure after the Broadcom acquisition face the same choice between expensive renewals, fragile storage and hardware they would rather not replace. The question is whether they modernize on their own terms, or after the next outage forces the decision.
Let's Talk
If your infrastructure is holding your business back, Nubius can assess your environment and show you what a low-risk path off VMware looks like.