CASE STUDY | M&A Integration: Microsoft 365 + Atlassian

Beating the Clock on an M&A Carve-Out

How a Nubius Solutions customer brought an acquired division into its environment in 5 weeks, over the holidays, with restricted access to the seller's systems, and without a single end-user complaint

5 weeks

to complete the integration, with the holidays in the middle

1 week

to spare inside the customer's 6-week window

0

end-user complaints across all 32 migrated users

3.7M+

email messages migrated

1.2M+

OneDrive and SharePoint files migrated

29K+

Jira issues and ~20K Confluence pages moved

Buyer: A rapidly-growing SaaS provider serving utility companies.

Deal: A carve-out. The buyer acquired one utilities-focused division of a larger technology company, not the whole company.

Scope: 32 end users (44 accounts including service accounts) moving from the seller’s environment into the buyer’s: Exchange mail, OneDrive, SharePoint, Microsoft Teams conversations, and Atlassian Jira and Confluence.

Timeline: A fixed 6-week window over the holiday season. Completed in 5 weeks, with a week to spare.

Nubius role: End-to-end integration: discovery, access and tooling design, migration execution, validation, and project management.

The Deal Closes. The Clock Starts.

When a buyer acquires a division instead of a whole company, the integration work is harder, not easier. The seller is still running its business on the same systems. Access is limited to what belongs to the division. Every mailbox, file, chat and ticket has to be separated from the parent company’s data and moved without disrupting the people who depend on it.

The window to move the acquired division’s entire collaboration environment was six weeks, spanning the year end holiday season.

The Challenge

  • No admin access to the source. The seller granted access only to what related to the acquired division. Migration tools assume broad admin rights; without adapting them, nothing could be migrated at all.
  • Selective migration. Only the division’s users, sites, teams and projects could move, and nothing belonging to the seller.
  • Platforms that resist migration. Restrictions on the seller’s tenant blocked the standard Teams migration path, and the division’s Jira and Confluence data could not be migrated directly from the seller’s Atlassian instance.
  • Zero tolerance for disruption. 32 people had to keep working through the transition, while the customer’s IT team replaced their laptops in parallel.
  • The calendar. Holidays, time off and approvals on both sides of the deal, inside a fixed six-week window.

How Nubius Delivered

Nubius ran the integration on the same six-phase framework it uses for every engagement, with one shared project plan, a dedicated channel with the customer, and weekly review calls. Here is how each phase played out.

Phase 1 — Discovery

In the first days, Nubius inventoried everything in scope: 32 end users in 6 groups (44 accounts including service accounts), about 357 GB of mail, about 352 GB of OneDrive data, 10 to 15 SharePoint sites, Teams channels and chats, 7 Confluence spaces, 4 Jira projects, service accounts, distribution lists, guest users and third-party integrations. Result: a precise scope before a single byte moved.

Phase 2 — Prerequisites & Requirements

This is where the carve-out constraints hit. With access limited to the division’s data, Nubius adapted the tooling and permission model instead of waiting for access that would never come. The seller provisioned a dedicated service account, CloudFuze was set up to work within the restricted permissions, and each of the 32 users was authorized individually.

Nubius mapped every source user, group, site and team to its destination, created and licensed the accounts on the buyer’s side, and audited both environments for user, group, project and space name conflicts. For Atlassian, Nubius worked with the seller to stage the division’s Jira and Confluence data in a separate instance, giving full access to exactly the data in scope and nothing else.

Phase 3 — Kickoff

Both teams agreed on stakeholders, owners and sign-off for each phase, how and when users would be notified, and whether to migrate in batches or all at once. Holidays and time off were built into the timeline from day one, so the schedule held through the season. No black boxes: everyone knew what was happening, when, and who owned it.

Phase 4 — Implementation

Nubius validated the approach with a pilot of three users before running the initial syncs for mail, OneDrive, SharePoint and Teams. Users kept working on the seller’s systems until final cutover.

  • Microsoft 365: mail, OneDrive and SharePoint migrated with CloudFuze through initial and delta syncs, then a final sync at cutover.
  • Teams: where the tool’s restrictions blocked the standard path, Nubius moved the conversations directly through the Microsoft API.
  • Atlassian: after a change freeze on the source, Nubius migrated Jira and Confluence from the staging instance into the buyer’s Atlassian cloud.
  • Cutover: users were notified ahead of time, distribution lists, service accounts and third-party integrations were reconfigured, and the final sync completed.

Phase 5 — Post-Implementation

Nubius validated the migrated data, monitored every platform, and confirmed access with end users. Because the seller could not provide a complete permission map, the remaining permissions were finalized after cutover with the buyer’s team leads. That was the only work left after cutover. End users were engaged for follow-ups, and no further issues were reported.

Phase 6 — Handoff & Closure

Nubius delivered a final report with migration results per user and per platform, completed backups and data exports, confirmed there was no remaining activity on the source, and closed out the source environments. The customer’s leads signed off on the migration.

What Moved

PlatformMigrated
Exchange mail32 mailboxes; ~3.77 million emails
OneDrive32 accounts; ~942,000 files
SharePoint20 document libraries; ~270,000 files
Microsoft TeamsTeam channels, group chats and direct messages, all but two conversations
Confluence7 spaces; ~20,000 pages and ~4,300 attachments
Jira4 projects; ~29,400 issues, ~112,000 comments and ~23,900 attachments

Note: Only two Teams conversations could not be retrieved because of security policies on the seller’s tenant.

How Constraints Were Handled

ConstraintRiskHow Nubius handled it
Restricted source accessSeller exposed only the division’s data; standard migration tooling expects tenant-wide admin rightsReworked tools and permissions to run inside the access granted: seller-provisioned service account and per-user authorization in CloudFuze
Carve-out, not full companyPulling the seller’s non-division data, or missing the division’sUser, site, team and group mapping on every platform so only the division’s data moved
Atlassian could not migrate directlyJira and Confluence history stranded in the seller’s instanceSeller staged the division’s data in a separate Atlassian instance; Nubius ran the final migration from there
Teams migration limitsChat history lost; tool restrictions on the seller’s tenantMigrated conversations directly through the Microsoft API; all but two conversations recovered
Holiday-season deadlineApprovals, freezes and time off compressing a 6-week windowHolidays and time off planned into the schedule at kickoff; one shared project plan and weekly reviews
Incomplete permission dataUsers unable to reach content after cutoverRemaining permissions finalized after cutover with the buyer’s leads and confirmed with end users

The Results

  • Done in 5 weeks: the full integration was completed with a week to spare in the 6-week window, with the holidays in the middle.
  • No end-user complaints: 32 people moved to the buyer’s environment and kept working.
  • Only the division’s data moved: mapping on every platform kept the seller’s data where it belonged.
  • Full history kept: mail, files, Jira issues with comments and attachments, and Confluence pages.
  • Smooth on both sides of the deal: the seller’s IT team called it the smoothest engagement they had worked on.

“We have never worked with a company where things went so smoothly and worked from the very beginning.” — IT lead, selling company

The Bigger Picture

In M&A, IT integration is where deal value either shows up on time or slips. Carve-outs add a layer most teams underestimate: restricted access, shared systems, and a seller who has their own business to run. Nubius has done this repeatedly, for this buyer and others, and brings a process that works within the limits of the deal, not just ideal conditions.

Let's Talk

If you have an acquisition closing, or a carve-out on the horizon, Nubius can help you scope the integration before Day 1 and deliver it on your timeline.

Scroll to Top